- Duininck Inc. paves roads for site, R & G Construction finishes final grade on site
- MPCA approves NPDES permit modification.
- Highwater Ethanol, LLC receives first loads of corn on July 24, 2009
|
|
- Accepted Substantial completion of facility on June 23, 2009 from Fagen Inc.
- Fencing installed by Century Fencing around perimeter of site.
|
|
- Rail system approved for rail traffic
|
|
- Grains receiving building completed
|
|
- Occupied Admin Building moving from office location downtown Lamberton
- Boiler System arrives from Indeck Boiler
|
|
|
|
|
|
- Selected "zero discharge" option for ethanol plant water discharge.
- Conducted archeological study of plant site and utility corridors.
|
|
- Filed SB-2 with US Securities Exchange Commission.
- Filed environmental permits with Minnesota Pollution Control Agency.
- Signed "Lump Sum Design Build Contract" with Fagen, Inc.
- Obtained option on three adjacent parcels of land in Redwood County, Minnesota.
|
|
- Purchased option for 57 acres along US Hwy 14 & DM&E railroad.
- Purchased option on 7 acres from City of Lamberton's EDA park along DM&E railroad.
|
|
- Signed grain procurement contract with Meadowland Farmers Elevator of Lamberton, MN.
|
|
- Signed "letter of intent" with Fagen, Inc. of Granite Falls, MN to build 50 mgy ethanol facility.
- Seed stock investors raised $1,180,000 for start up development costs.
- Purchased option on 68 acres of land along US Hwy 14 and DM&E railroad.
|
|
- Selected name and organized Highwater Ethanol, LLC.
- Founders invested of $500,000 of equity.
- Selected Fagen Inc/ICM, Inc. as design-build contractor.
|
|
- Interviewed 3 design-build construction companies.
|
|
- Drilled high capacity well at Site 1.
|
|
- Selected board of governors and officers.
|
|
- First organizational meeting.
|