History 2007

November
  • Dirt work begins
September
  • $45 million equity raised
August
  • Obtained Permits from MPCA
April
  • SEC approval and start of Equity Drive.
March
  • Closed on two parcels of land for which we had exercised land options. (116 acres)
February
  • Membership control agreement to meet SEC.

History 2006

December
  • Exercised two options on land in Redwood County, Minnesota
October
  • Selected "zero discharge" option for ethanol plant water discharge.
  • Conducted archeological study of plant site and utility corridors.
September
  • Filed SB-2 with US Securities Exchange Commission.
  • Filed environmental permits with Minnesota Pollution Control Agency.
  • Signed "Lump Sum Design Build Contract" with Fagen, Inc.
  • Obtained option on three adjacent parcels of land in Redwood County, Minnesota.
August
  • Purchased option for 57 acres along US Hwy 14  & DM&E railroad.
  • Purchased option on 7 acres from City of Lamberton's EDA park along DM&E railroad.
July
  • Signed grain procurement contract with Meadowland Farmers Elevator of Lamberton, MN.
June
  • Signed "letter of intent" with Fagen, Inc. of Granite Falls, MN to build 50 mgy ethanol facility.
  • Seed stock investors raised $1,180,000 for start up development costs.
  • Purchased option on 68 acres of land along US Hwy 14 and DM&E railroad.
May
  • Selected name and organized Highwater Ethanol, LLC.
  • Founders invested of $500,000 of equity.
  • Selected Fagen Inc/ICM, Inc. as design-build contractor.
April
  • Interviewed 3 design-build construction companies.
March
  • Drilled high capacity well at Site 1.
February
  • Selected board of governors and officers.
January
  • First organizational meeting.

 

 