History 2009

September

July

  • Duininck Inc. paves roads for site, R & G Construction finishes final grade on site
  • MPCA approves NPDES permit modification.
  • Highwater Ethanol, LLC receives first loads of corn on July 24, 2009

June

  • Accepted Substantial completion of facility on June 23, 2009 from Fagen Inc.
  • Fencing installed by Century Fencing around perimeter of site.

May

  • Rail system approved for rail traffic

April

  • Grains receiving building completed

March

  • Occupied Admin Building moving from office location downtown Lamberton
  • Boiler System arrives from Indeck Boiler

February


History 2008

Summer/Fall

August

  • Highwater Ethanol Groundbreaking - Click here to see invitation or here to see photos.

Spring

April

  • First annual meeting held on April 18, 2008


History 2007

November

  • Dirt work begins

September

  • $45 million equity raised

August

  • Obtained Permits from MPCA

April

  • SEC approval and start of Equity Drive.

March

  • Closed on two parcels of land for which we had exercised land options. (116 acres)

February

  • Membership control agreement to meet SEC.


History 2006

December

  • Exercised two options on land in Redwood County, Minnesota

October

  • Selected "zero discharge" option for ethanol plant water discharge.
  • Conducted archeological study of plant site and utility corridors.

September

  • Filed SB-2 with US Securities Exchange Commission.
  • Filed environmental permits with Minnesota Pollution Control Agency.
  • Signed "Lump Sum Design Build Contract" with Fagen, Inc.
  • Obtained option on three adjacent parcels of land in Redwood County, Minnesota.

August

  • Purchased option for 57 acres along US Hwy 14  & DM&E railroad.
  • Purchased option on 7 acres from City of Lamberton's EDA park along DM&E railroad.

July

  • Signed grain procurement contract with Meadowland Farmers Elevator of Lamberton, MN.

June

  • Signed "letter of intent" with Fagen, Inc. of Granite Falls, MN to build 50 mgy ethanol facility.
  • Seed stock investors raised $1,180,000 for start up development costs.
  • Purchased option on 68 acres of land along US Hwy 14 and DM&E railroad.

May

  • Selected name and organized Highwater Ethanol, LLC.
  • Founders invested of $500,000 of equity.
  • Selected Fagen Inc/ICM, Inc. as design-build contractor.

April

  • Interviewed 3 design-build construction companies.

March

  • Drilled high capacity well at Site 1.

February

  • Selected board of governors and officers.

January

  • First organizational meeting.

 

 