Photo Gallery
May 13, 2009
|
|
RO Pond lined |
View of silos |
May 7, 2009
|
|
|
Enviropan at Ethanol Rail loadout |
Grain Receiving Bldg looking East |
Grain Receiving Bldg looking West |
April 23, 2009
|
|
|
Administration Building |
Boiler and Economizer in place |
Looking North across top of Process building |
|
|
|
Looking North at Energy Center |
Looking West over Tank Farm and Ponds |
Rail spur looking East |
|
|
|
Rail system looking West |
RO Pond before liner |
Top of Corn Leg on top of Silos |
|
|
|
View of CLS Bldg, outside storage tanks & silos in background |
|
|
April 14, 2009
|
|
|
Construction on the Grain Receiving Bldg |
Thermal Oxidizer connection to Boiler package |
View of Energy Center |
March 19, 2009
|
|
|
Indeck Boiler arriving by rail |
Indeck Boiler in place |
Indeck Boiler package |
|
|
|
View of Indeck Boiler |
View of railsiding looking West |
View of the Indeck Boiler arriving |
|
|
|
Well site #1 |
March 5: Boiler Economizer in place |
|
February 26, 2009
|
|
Fire Water Tank |
Setting the Boiler Economizer package |
February 17, 2009
|
|
|
CO2 Scrubber Stack & Support Structure |
Cooling Water Supply & Return Lines |
Corn Leg & Corn Dust Bag House Installation |
|
|
|
Methanator Bio Reactor Tank Insullation |
Process & Fire Water Storage Base |
Stillage Tanks & Energy Center facing Northwest |
|
|
|
Thermal Oxidizer Stack |
|
|
October 14, 2008 - January 6, 2009
|
|
|
1/6/09: Interior of main reception area in Admin bldg. |
1/5/09: MCC room – grain storage. |
12/18/08: Thermal oxidizer stack in place. |
|
|
|
12/18/08: Setting the thermal oxidizer stack. |
12/18/08: Energy center awaiting boiler delivery by rail. |
12/15/08: Switchback staircase on grain storage silos. |
|
|
|
12/15/08: NE corner of water treatment building. |
12/15/08: Grain receiving building basement. |
12/15/08: Rail spur to DDGS & ethanol loadout. |
|
|
|
11/26/08: Administration building progress. |
10/17/08: Silo pour – end of Day 2. |
10/17/08: Priming the ethanol storage tanks. |
|
|
|
10/16/08: View of Lamberton from the top of the silos during the pour. |
10/15/08: Admin basement floor |
10/15/08: Silo Pour: Day 2 |
|
|
|
10/15/08: Silo Pour: Day 2 |
10/15/08: Silo pour under light |
10/14/08: Silo Pour |
October 31, 2008

|

|
Photo taken October 31, 2008 |
Looking east toward Lamberton |

|

|

|
|
Looking north.......... ~ Photos taken by Elton Goeman |
|
October 3, 2008

|

|

|
Aerial towards grain silos |
CLS Building soil sub-grade |
Skyline view |

|

|

|
Grains recieving building floor: Day 1 |
Silo slip form construction |
Cooling tower finished |

|

|

|
Rail siding looking east |
Tank farm near completion |
Beginning silo pour |
Aerial of Groundbreaking and Plant Layout - Click image to see entire plant view.

August 2008 - Groundbreaking Ceremony

|

|

|
Board Chair Brian Kletscher welcomes the approximately 100 attendees.
|
Gerald Woodley, field staff for Sen. Norm Coleman, brings greetings and congratulations from Washington.
|
Ron Fagen at the podium.
|

|

|

|
State Sen. Jim Vickerman spoke on ethanol's role in rural economic development.
|
Board members and dignitaries putting the shovels to work.
|
MN Corn Growers served refreshments. Thank You!! |
July 2008
|
|
|
7-25-08: DDG building perimter wall footings |
7-30-08: Tank Farm: Ethanol storage tanks |
7-31-08: Top put on third Ferm |
June 30, 2008
|
|
|
Stillage alley slab |
Energy Center column pad methanator area |
Column pads evap area |
|
|
|
Second tier on ferm |
Ferm alley looking west |
Ferm 3, first tier |
|
|
|
Energy Center common wall pour |
Dryer B pillars |
Stillage alley tank bases |
|
|
|
Stillage alley looking west |
Energy Center common wall |
10 inch water main, Harvest Ave. |
April 14, 2008 Aerial Photos - Click on pictures for larger image.

|

|

|
| 2008 Annual Meeting
At the sign-in table |
2008 Annual Meeting
President B. Kletscher delivering the board's presentation at the 2008 annual meeting held April 18, 2008 in Lamberton. |
April 2008
President B. Kletscher signing the loan documents. |

|

|

|
| April 2008
T. VanDerWal (board secretary),
K. Stroup (board legal counsel),
and B. Kletscher (board president)
after loan closing. |
April 2008
A completed dryer footing excavation. |
Exterior process tanks. |

|

|

|
March 2008
Forms in place and ready to pour concrete. |
March 2008
Pouring a ferm tank. |
March 2008
Concrete pumper trucks in position to deliver concrete for ferm tanks. |

|

|

|
February 2008
Footings before backfill installation. |
February 2008
More footing work. |
February 2008
Building forms for the first footings. |
Week 7
|
|
|
Temporary electrical work completed |
Geopier modulus strength test:
exceeded design performance! |
Geopier installation continues |
Week 6
|
|
|
 |
Setting up for Geopier strength test |
Installing temporary electrical power |
Directional boring underground cables |
Geopier installation continues |
Week 5
|
|
|
|
Installing geopiers
(381 remaining) |
Step 1 - drill 13ft deep cavity |
Step 2 - Add crushed rock |
Step 3 - compact rock with tamper, repeat steps 2 & 3 until filled |
Week 4
|
|
|
|
Spreading corn stalks to minimize frost |
First temporary structure |
Marking geopier locations |
Geopier equipment |
Week 3
|
|
|
|
Installing Storm-water pond outlet |
Removing frozen soil for grain silos |
Compacting and spreading fill for grain silos |
Geotextile fabric placed under gravel for roadways |
Week 2
|
|
|
|
Granular fill for Process Building |
Stripping storm-water pond |
Shaping storm-water pond berm |
Unloading granular fill ...
on-the-go! |
|
|
|
|
DDG building |
Energy Center Building |
Adding 1 ft. 'lift' of granular
fill for Process Building |
TERRACON engineer
checking fill compaction |
Week 1
|
|
Stripping top soil |
Energy Center excavation |
|
|
Second load of gravel for Energy Center footing |
Scrapers working in tandem |
Preparing for Construction
|
|
First delivery - 3 miles of silt fence. |
Equipment ready to go. |
|
|